%u2022 Milestone gas-in tercapai pada tanggal 14 Agustus 2022.%u2022 Milestone GoS 20% capacity dicapai pada tanggal 20September 2022 (sales gas ke PGN minimum 8~18 mmscfd).%u2022 Milestone GOS up to 40% capacity dicapai pada tanggal 6November 2022.%u2022 Milestone acid gas in to Process-2 dicapai pada tanggal 7 Juli2023.%u2022 Pengujian 1st Performance Test Run (periode 17 - 28 Juli 2023) hanya berlangsung selama 10 menit karena terdapat trip padasystem 234 propylene HH temperature%u2022 Pengujian 2nd Performance Test Run (periode 22 - 25 Agustus2023) berlangsung selama 57 jam dari rencana 72 jam.%u2022 Pengujian Re-Performance Test Run (22 November 2023 - PTR mencapai 11 hour, reduce due to demand)%u2022 Pengujian Re-Performance Test Run (5 December 2023 - PTRselama 24 jam, reduce due to demand)%u2022 Pencapaian operasi yang stabil untuk area Process-1 andProcess-2 tercapai sejak 3 November 2023. Berhasil mencapaiperformance test selama 92 jam @192 MMSCFD.%u2022 Sedang berlangsung aktivitas closing punch list andpelaksanaan repair work.%u2022 Persetujuan Placed Into Services (PIS) dari SKK Migas diperoleh untuk area Process-1 dan Supporting Facilities Gas Processing Facilities %u2013 Jambaran Tiung Biru dengan tanggal efektif sejak14 December 2023 untuk 71.15% dari total acquisition value JTB GPF facility assets berdasarkan nilai persetujuan AFE.%u2022 Pembahasan dengan BPKP terkait usulan change order (CO)dari Kontraktor pada tanggal 19 %u2013 22 Desember 2023 danmekukan tindak lanjut Notulen Rapat dengan BPKP.%u2022 The gas-in milestone was reached on August 14, 2022.%u2022 The GoS 20% capacity milestone was achieved on September20, 2022 (gas sales to PGN minimum 8~18 mmscfd). %u2022 The GOS milestone of up to 40% capacity was achieved onNovember 6, 2022.%u2022 The acid gas into Process-2 milestone was reached on July 7,2023.%u2022 The 1st Performance Test Run (period July 17 %u2013 28, 2023) onlylasted for 10 minutes because there was a trip in the 234propylene HH temperature system%u2022 The 2nd Performance Test Run (period August 22 %u2013 25, 2023)lasted for 57 hours out of the planned 72 hours.%u2022 Re-Performance Test Run (November 22, 2023 - PTR reached 11 hours, reduce due to demand)%u2022 Re-Performance Test Run (5 December 2023 - 24-hour PTR,reduce due to demand)%u2022 The achievement of stable operations for the Process-1 andProcess-2 areas was achieved since November 3, 2023. Successfully achieved performance test for 92 hours @192 MMSCFD.%u2022 Closing punch list and repair work are ongoing.%u2022 Placed Into Services (PIS) approval from SKK Migas wasobtained for Process-1 and Supporting Facilities Gas Processing Facilities %u2013 Jambaran Tiung Biru area with an effective date ofDecember 14, 2023, for 71.15% of the total acquisition value ofJTB GPF facility assets based on the AFE approval value.%u2022 Discussion with BPKP regarding the proposed change order(CO) from the Contractor on December 19 %u2013 22, 2023 andfollow up on the Minutes of the Meeting with BPKP.214 Laporan Tahunan %u2022 PT Pertamina Hulu EnergiPEMBAHASAN DAN ANALISIS MANAJEMENMANAGEMENT DISCUSSION AND ANALYSIS 4 5 6 7